Reid Street Revitalization Update

City News July 17, 2018
 
Reid Street project update
Crews are preparing and cleaning the construction site for Billy Barker Days. Safety fencing will be on site in order to keep the construct site safe.  A small crew will also work to ensure the safety of the construction site during this weekend’s events. On Monday, July 23 sidewalks in Phase I will begin to be poured.

 

Quesnel City News Release

Reid Street project update – July 4, 2018
In Phase I, concrete curbs will be poured Thursday through Saturday. This critical, time-sensitive work will create disruptions to pedestrian traffic. Extra flaggers and security personnel will be on site to direct pedestrians and to protect the poured curbing.
In phase II, crews will continue installing the water main.
Thank you for your cooperation!

 

City News – Reid St Project Update

City News June 26, 2018
 
Reid Street project update
Crews completed the pulverization of Phase II on June 21. They are now excavating and preparing for pipe installation. A water leak was discovered in Phase II when crews were excavating. City crews were able to temporarily stop the leak which will be replaced with the new water main and water supply connections.
In Phase I, all of the street light bases have been installed and crews are preparing for curb works.
Take a look at our parking map to see free public parking options. Phase II Parking map