WFC Construction Update

Construction Update:

The pouring of concrete continues to be the focus of construction.  The first of the suspended slab concrete pours was completed on Friday for a portion of the second floor of the building.  This section included the banquet room and potions of the north and west concourses.  The contractor, Vic Van Isle Construction, is preparing to pour the second suspended concrete slab at the south west corner of the building later this month and we can expect to see some of the second-floor support pillars being erected in the coming weeks.

Schedule and Budget:

The project continues to be on schedule for completion by September 2017.  The project continues to be on budget for $20.6 million.

Fundraising:

The Seat Sale and Mural Sale continue. If you haven’t sponsored a seat or made a donation to the project, contact Alex by email at: arenaproject@quesnel.ca.