Reid Street Revitalization project update
The majority of the water main has been installed in Phase I. This week, crews are beginning to install the storm pipe in Phase I and street lights. Thursday, May 24 through Saturday, May 26, crews will be working in the intersection of Reid St and Carson Ave. There will be single lane traffic on Carson Ave during this time. This is an active construction site, please make sure to follow ALL construction signage for your safety and the safety of the workers.