WFC Construction Update

West Fraser Centre

Construction Update:

 The steel trusses and decking are in place for the roof structure.  The Insulated Metal Panels for the building’s exterior walls are being installed and are in place for most of the north and west portions of the building.   The contractor hopes to have the building completely enclosed by the end of January.  The masonry block work continues on the site with work progressing on the interior walls. The mechanical duct work inside the building is underway.

Schedule and Budget:

 The project continues to be on schedule for completion by September 2017 and on budget for $20.6 million.  Close to $3 million has been spent on local contractors and suppliers to date on the project.